Construction Update 2017-09-19

20 Sep 2017

Dufferin would like to announce that the Highway 401 westbound on and off ramps at Veterans Memorial Parkway is scheduled to be opened up to traffic on Monday September 25, 2017. We thank you for your patience during this past little while as there has been a lot underway.

This last month has seen us pour everything from concrete curbs, medians, barrier walls, light pole bases, approach slabs, and the slopes underneath the bridge. Overhead signs and guide rails have also been put up. The bridge is currently being cleaned and painted, with that work wrapping up in the next couple of weeks.

Paving is well underway throughout the site and should be done in three to four weeks. We appreciate your continued patience and look forward to opening up the rest of the project by the end of October.