Construction Update 2017-07-18

18 Jul 2017

The bridge deck was successfully poured last week Tuesday July 11th, 2017. The formwork is being removed, and backfilling of the abutments will begin in the next week. The barrier wall on the bridge is the next component to be poured and that is scheduled to be done in the next couple of weeks.

On the north side of the highway, the westbound on and off ramps are being graded. They are scheduled to be reopened to traffic by early September.

On the south side we are gearing up to pour the curb and centre median along the extension of Veterans Memorial Parkway. That work is scheduled to begin next week.

Looking ahead, paving is scheduled to start mid to late August and will run for about a month. Four overhead signs are scheduled to be installed as well in late August.