Construction Update 2017-06-27

27 Jun 2017

The formwork and rebar for the bridge deck is being installed to get ready for the concrete pour scheduled for early July.

North of Hwy 401, work is in full swing. Grading of the westbound off ramp is well underway, and work has begun on the new westbound on-ramp.

South of the highway, the ditches have been cleaned up where sediment built up over the winter and spring. Grass has also been sprayed on the banks and in the ditches.