Construction Update 2017-06-09

09 Jun 2017

Reconstruction of a section of Wilton Grove Road was completed June 5th and 6th.  The grading work on the Hwy 401 eastbound on and off ramps is moving along, and the westbound off ramp work has now begun.

The girders over the 401 were also installed June 5th and 6th.

All of the existing asphalt on the westbound ramps has been milled off to prepare for the grading work in those areas

In the next couple of weeks, we will continue installing pipe culverts and sewers, as well as grading the new on and off ramps at Veterans Memorial Parkway. We will also be installing the precast deck panels that sit on top of the girders. The bridge deck itself is scheduled to be poured in early July.