Construction Update 2017-05-29

29 May 2017

Work in the centre median has been completed and the inside lanes have been reopened.

The south abutment has been poured, and formwork for the bridge deck on both sides of the highway has started going up.

Reconstruction of a section of Wilton Grove Road is almost completed and is scheduled to be paved by the end of the month. The Hwy 401 eastbound on and off ramps is coming along, and the westbound ramp work has now started.

As of today, there is no access to or from Hwy 401 from Veterans Memorial Parkway.