Construction Update 2016-11-14

14 Nov 2016

Traffic Restrictions

  • Minimal. The shoulder is closed on the E-N off-ramp for swamp excavation

Look Ahead Schedule

  • Test piles to be placed on November 28, 2016
  • Construction will continue until winter shutdown mid-December

Construction at a Glance

Week of November 14, 2016

  • Continue removing and replacing swamp material in the northeast quadrant
  • Continue grading of the VMP extension
  • Begin seeding ditches alongside VMP extension

Week of November 7, 2016

  • Plant trees and shrubs, seeding alongside Crinklaw Drain
  • Continue grading of the Veterans Memorial Parkway extension
  • Continue placing topsoil on ditches of VMP extension
  • Begin removing and replacing swamp material in the northeast quadrant

Previous work

  • Trees and shrubs cleared
  • Crinklaw drain realigned
  • Retaining walls installed on each end of Crinklaw Drain box culvert and in the
    southeast quadrant